Downtown Construction Progressing

On Monday Smoky Hill Construction will be closing North Santa Fe Avenue from Iron Avenue to Ash Street.

  • Northbound traffic on Santa Fe from Walnut Ave to Ash St will be detoured east on Walnut, north on 5th Street to Ash Street and then west to return to Santa Fe Ave.
  • Southbound traffic on N. Santa Fe Ave will be able to continue south.
  • Ash Street intersection will remain open until water line work nears this intersection.

Weather dependent, the outlook for Santa Fe progress is as follows:

4/22-4/26Pavement/Sidewalk removal from Iron to Ash
4/22-6/10Watermain, fire protection and services from Iron to Ash (east 1/2)
4/25-5/10Sidewalk from Iron to Ash
5/9Open Iron intersection for east/west traffic
5/10-5/24Southeast Ash quadrant closures

 

All businesses in this work area will have access to their doors.  Plenty of downtown parking exists in the public parking lots and along Fifth Street and Seventh Street.