Graham County Takes Another Step Toward Wind Farm

KSAL StaffMay 6, 2013

A northwest Kansas county is closer to having its own 70-megawatt wind farm.

The Graham County Commission has approved a conditional use permit for the Ringneck Prairie Wind Farm 6 miles south of Hill City.

The Hays Daily News reports that details remain to be worked out, but last week’s approval of the conditional-use permit, as well as road and payment agreements, means the project is on track.

The county’s economic development director, Kirk Schweitzer, says road work, pad sites, underground power lines and other steps could be completed in the fall, with towers going up next spring.

The wind farm is expected to create eight permanent jobs once it is operating.

Copyright © Rocking M Media, 2020. All Rights Reserved. No part of this story may be reproduced without Rocking M Media’s express consent.

CATEGORIES :

RELATED POSTS

Double Murder Victims Identified

January 7, 2018 9:45 am

Plans For NW Kansas Wind Farm Move Forward

November 26, 2013 6:42 pm



STAY IN TOUCH!

GET OUR APP!

LATEST POSTS

Kansas Amber Alert Cancel...
October 24, 2020Comments
Big BooBash Virtual Costu...
October 24, 2020Comments
Upland Game Bird Seasons ...
October 24, 2020Comments
38 New Saline County COVI...
October 23, 2020Comments

LATEST TWEETS

Read all tweets
© 2007 - 2020 - EEO  - KABI  - KSAL-AM  - KSAL-FM  - KVOB  - KYEZ  - KZUH